Oracle force majeure notice sent to developer of Project Jupiter AI data center in New Mexico

The notice to a Blue Owl development unit could let Oracle defer payments if the 2.45-gigawatt Stargate campus misses its 2028 target amid gas pipeline and permit delays.

By · Editor

· 3 min read · Fact-checked

The 60-second brief

  • 1Oracle sent a force majeure notice to a Blue Owl Capital unit over the 2.45-gigawatt Project Jupiter campus in Santa Teresa, New Mexico, Bloomberg News first reported on Sept. 24, 2026.
  • 2Energy Transfer’s gas pipeline for the site is now slated for February 1, 2027, nearly six months late, after state permit denials.
  • 3Oracle says the project remains on its planned schedule and such notices are commonplace; its shares closed down 3.47% on Sept. 24.

The news

Oracle has sent a force majeure notice to Blue Owl Capital, the owner of STACK Infrastructure, which is developing the Project Jupiter data center campus in Santa Teresa, New Mexico. Bloomberg News first reported the Oracle force majeure notice on Thursday, Sept. 24, 2026.

A force majeure notice asserts that events outside a party’s control may prevent it from meeting contract obligations. In this case, it could allow Oracle, the campus’s main tenant, to defer payments if the facility misses its planned 2028 start. The campus, part of the Stargate AI infrastructure effort involving Oracle and OpenAI, is designed for 2.45 gigawatts of capacity.

Energy Transfer’s gas line for the site, first due in September 2026, now has a February 1, 2027 start after the New Mexico State Land Office repeatedly rejected permits for its proposed route, Bloomberg reported; Searchlight New Mexico said it still lacks Land Office approval. An air-quality permit for the campus’s Bloom Energy fuel cells is also pending, with a state decision due by November 23, TechCrunch reported.

In a Sept. 24 post on X, Oracle said the project remains on its planned schedule; Oracle Vice President Michael Egbert told The New Mexican such notices are commonplace in developments of this scale and do not by themselves establish a delay. STACK said the notice does not change the financial commitments to the project. Oracle shares closed down 3.47% on Sept. 24 after falling almost 5% early, Searchlight New Mexico reported.

The numbers

Designed campus capacity
2.45 GW
Target online date
2028
Delayed pipeline in-service date
Feb. 1, 2027
Oracle stock close, Sept. 24
−3.47% (per Searchlight New Mexico)

Why CEOs should care

For customers counting on Oracle Cloud Infrastructure capacity — including AI labs and enterprises that signed large compute contracts — this is a reminder that announced gigawatts are not delivered gigawatts. Whatever Oracle intends, a force majeure notice is a legal hedge against delay. Buyers of future AI capacity should ask vendors which specific sites back their commitments and what happens contractually if those sites slip.

The underlying constraint is energy. Jupiter depends on a gas pipeline and on-site fuel cells, both tied up in permitting. Leaders planning AI workloads over the next few years should treat power availability as the gating factor for capacity pricing and timelines, not just chip supply.

The bigger picture

About 20 banks lent $18 billion to help build Jupiter, Bloomberg reported, and those loans are being quoted at 89 to 91 cents on the dollar, Searchlight New Mexico said, citing the Financial Times. Our read: stress at a site this large draws scrutiny because much of Oracle’s growth outlook rests on bringing AI capacity online on time.

What’s next

The New Mexico air-quality permit decision due by November 23 is the next milestone to watch.

What “Fact-checked” means

Fact-checking means testing a story’s facts against the evidence before it is published. This story went through at least two separate checks before this version was published.

What we checked
Its names, figures, dates, job titles, quotes and who said what were checked against the story’s sources, including its main source where it could be opened. The headline was checked for accuracy and overstatement.
How
A first check reviewed the whole story. If it passed, a second, skeptical check went back to the sources to look for mistakes in the most important facts. If a check flagged the story, it was edited to fix the problems found, and a separate re-check then reviewed the whole story again.
Who
The checks are made by our newsroom, as steps kept separate from the writing, under rules set by our editor, . A story the checks still flag is held for the editor, who decides whether it is fixed, published or dropped.
If something is wrong
“Fact-checked” does not mean error-free. If a material error is found after publication, we correct the story and add a note saying what changed. Report an error

How we fact-check →

Companies in this story

OracleData centersStargateEnergy

Earlier coverage of Oracle

All Oracle coverage →

Written by

Editor · Technology & Business Writer

Hussein is a writer and business technology enthusiast focused on the intersection of technology, entrepreneurship, finance, artificial intelligence, and digital innovation.

CoversAICybersecurityBig TechSaaSStartupsFintech

About this story. Researched from primary sources whenever they are available and fact-checked before publication.

Published by Tech CEO Daily, an independent publication. Masthead · Editorial standards

Follow Tech CEO Daily on Facebook for the day’s top stories in your feed.

Free newsletters

The technology briefing for people running businesses.

Daily, weekly, bi-weekly or monthly. You choose.

How often

The Daily Brief · Monday to Saturday, 7 a.m. ET

Free forever. One click to unsubscribe. We never sell your email.